B 200 Furniture Fixtures Equipment (FFE) and Finishes Renovations Project

Project Start Date: Spring 2020
Construction Start Date: August 2021
Project Completion Date: December 2021
Project Description:
The B200 Furniture, Fixtures, Equipment (FFE) and Finishes Renovations Project will provide a much needed facelift to the B200 building. From classrooms to offices to shared open spaces, all areas of the B200 is getting some much needed TLC.

PE 200 Gas Generator Project

Project Start Date: Fall 2021
Construction Start Date: April 2022
Project Completion Date: September 2022
Project Description:
The PE 200 Gas Generator Project will provide a continuous source of electricity for the PE 200 building.

The project is still in design with contractor selection February 2022. Construction will begin April 2022, and project completion September 2022.

Gym Bleachers Replacement Project

Project Start Date: Fall 2020
Construction Start Date: August 2021
Project Completion Date: April 2022 (Confirmed Supply chain delays)
Project Description:
The Gym Bleachers Replacement Project includes replacement of the telescoping bleacher system, upgrades to the existing fire alarm system in the PE200 building, and accessibility upgrades including: accessible entrances, drinking fountain/bottle fill stations, signage, restrooms and parking modifications.

Student Union

Project Start Date: Fall 2019
Construction Start Date: 2024
Project Completion Date: 2026‐2027
Gross Square Footage: 31,300 sf
Assignable Square Footage: 30,362 sf
Project Description:

B 200 Chemistry Labs Renovation

Project Start Date: Fall 2018
Phase I Construction Start Date: June 2019
Phase I Construction Completion Date: November 2019
Phase II Construction Start Date: March 2020
Phase II Construction Completion Date: December 2020
Phase III Construction Start Date: March 2021
Phase III Construction End Date: August 2021
Project Completion Date: Summer 2021

Scheduled Maintenance Campus-Wide Electrical Upgrades Project

Project Start Date: Fall 2021
Construction Start Date: Summer 2025
Project Completion Date:  February 2026 (early Spring 2026)
Project Description: 
The Scheduled Maintenance Campus-Wide Electrical Upgrades Project is providing upgrades to electrical breakers and switch gear across campus.

Replacement of electrical infrastructure equipment is currently underway with construction completion estimate for December 2025.

Campus-Wide Fire Alarm Controller Upgrades Project

Project Design Start Date: Spring 2020
Construction Start Date: March 2022
Project Completion Date: August 2022 (Confirmed supply chain delays)
Project Description:

The campus’ Fire Alarm System is getting campus wide upgrades to the system panels and sensors. The project was delayed due to campus shutdown and was started back up in 2021.

Due to supply chain delays, the project’s construction start date has been pushed forward to March 2022 with a new estimated completion date of August 2022.